Dear All
Over the next 2 weeks, we have planned closures of the southbound approach on the Swavesey junction overbridge, between the A14 eastbound entry slip and the A14 westbound J24b exit slip.
These closures are to allow us to safely undertake remedial work on the overbridge, which includes replacing damaged kerbing. Once complete, the temporary traffic management at the junction and on the A1307 eastbound approach to the roundabout will be removed.
The works are scheduled to take place over 10 nights, 6 nights this week (Monday – Saturday) and 4 nights next week (Monday – Thursday) between 9pm and 6am.
Monday 21 to Friday 25 (5 nights)
- Swavesey junction overbridge southbound (between A14 eastbound J24 entry slip and A14 westbound J24b exit slip)
Wednesday 23 to Friday 25 (3 nights)
- A14 westbound Swavesey J24b exit slip
Monday 28 to Friday 2 (5 nights)
- Swavesey junction overbridge southbound, including A14 westbound J24b exit slip and A14 westbound J24 entry slip
Signed diversions will be in place and special signs placed on the A14 eastbound for those exiting the main carriageway wishing to access Cambridge Services.
Kind regards
Maxine Wraith
Customer Lead
A14 Cambridge to Huntingdon
http://www.highwaysengland.co.uk/