A14 C2H – Planned road closures w/c 13 December 2021

The planned extended closure of the B1514 Brampton Road on Sunday 12 has been further delayed by one week and will now take place on Sunday 19 00:01 to 20:00. There will now be an overnight closure in order to jack up Span 3 on Saturday 11 between 8pm and 5am.

 

*Cancelled* Sunday 12 9pm – 6am

A1 northbound between Buckden roundabout and A14 westbound Brampton Interchange junction 22

…………………………………………………………….

A14 Cambridge to Huntingdon, Cambridgeshire: major improvements

We are currently carrying out finishing works for which we need to close lanes or carriageways on the A1, A14 and some local roads at times, usually overnight between 9pm and 6am, unless otherwise stated. A clearly signed diversion route will always be in place for closures.

For this week, the planned closures are:

Full closures

Monday 13 to Friday 17 (five nights)
• A10 northbound between the Milton junction 33 gyratory and Butt Lane
Vehicles will be diverted east on the A14 to Newmarket junction 37, north on the A142, west on the Ely Southern Bypass and then either south on the A10 for access or re-join the A10 northbound to continue their journey

Sunday 19 12.01am to 8pm
• B1514 Brampton Road between the RingGo car park and Edison Bell Way
Vehicles on the Huntingdon town centre side will be diverted onto the ring road, St Peters Road to A141 west to Brampton / Brampton Racecourse junction and into Brampton via B1514.

Vehicles on the Brampton side of the closure will follow this diversion in reverse.

For more information about this scheme, visit https://nationalhighways.co.uk/our-work/a14-cambridge-to-huntingdon/